360 Rail Services’ staff have performed rail planning, surveying, rail infrastructure design, and construction for the Casper Crude to Rail unloading facility in Casper, WY. They were able to work around a sensitive wetland environment successfully.

Crude Oil Transloading Facility Project
Woring in the process

This project included the construction of manifest tracks, multiple loop tracks, a bad order track, and 5 at-grade crossings. This project designed and constructed a track that allowed up to three unit trains to occupy the facility simultaneously.

We Surpassed Expectations On These Railway Projects

The 360 Rail Services expert team delivers outstanding solutions and provides value to every project.

Crude Oil Unloading Facility
Crude Oil Unloading Facility

360 Rail Services’ staff have performed rail construction for the BNSF-served Genesis Energy facility in New Orleans, LA.

Read More About the Project
Steel Facility Logistics Spur-1
Steel Facility Logistics Spur

360 Rail Services provided design and construction for a URPR-served logistics spur to a steel facility in Henderson, CO. 

Read More About the Project
Grain Transloading Facility
Grain Transloading Facility

Our experienced engineers and construction team overcame space limitations to create this facility capable of supporting an entire unit train in Alliance, NE.

Read More About the Project

LET'S GET TO WORK

Receive a Complimentary Concept